Possible Faults and Solutions During Operation of High Pressure Reactor
1. When there is no material in high pressure reactor, the heating and electric heating power sources must not be turned on, and the rated working pressure must not be exceeded during use. When using high pressure reactor, the cooling device must be turned off, which means that the remaining refrigerant in the kettle and jacket during the last reaction must be exhausted before materials can be input. During operation, start the stirrer first and then turn on the heating device. At the end of the reaction, the heating device and electric heating power switch should be turned off first, and then the stirrer should be turned off after 2 to 3 minutes.
2. After a reaction process is completed, the materials stuch on the inner wall of high pressure reactor should be washed away with warm water as soon as possible, and then the inner wall of the reactor should be completely and thoroughly cleaned with 40℃~50℃ alkaline water, and finally rinsed with clean water to achieve durable purpose.
3. When the reducer lubricating oil is found to be insufficient, it should be replenished immediately, and the oil bath heating medium oil should be replaced every six months.
4. For high pressure reactor, you should always pay attention to the working conditions of the entire equipment and reducer. The safety valves, pressure gauges, electric heating rods, electrical instruments, etc. on the jacket and the kettle cover should be checked regularly. If there is any fault, replace or repair it immediately.